Array
(
[0] => Array
(
[id] => 2
[name] => 首页
[category_id] => 221
[url] =>
[active] => 1
[position] => 1
[blank] =>
[is_out] =>
)
[1] => Array
(
[id] => 4
[name] => 氿上商城
[category_id] => 221
[url] => goods
[active] => 1
[position] => 2
[blank] =>
[is_out] =>
)
[2] => Array
(
[id] => 1
[name] => 学习园地
[category_id] => 221
[url] => news
[active] => 1
[position] => 5
[blank] =>
[is_out] =>
)
[3] => Array
(
[id] => 16
[name] => 氿上知道
[category_id] => 221
[url] => question
[active] => 1
[position] => 4
[blank] =>
[is_out] =>
)
[4] => Array
(
[id] => 5
[name] => 供求信息
[category_id] => 221
[url] => trade
[active] => 1
[position] => 3
[blank] =>
[is_out] =>
)
[5] => Array
(
[id] => 3
[name] => 软件下载
[category_id] => 221
[url] => jsyjj/list/409
[active] => 1
[position] => 6
[blank] =>
[is_out] =>
)
[6] => Array
(
[id] => 46
[name] => 氿上云管理
[category_id] => 221
[url] => yun/index
[active] => 1
[position] => 7
[blank] =>
[is_out] =>
)
[7] => Array
(
[id] => 22
[name] => 氿上花园
[category_id] => 221
[url] => garden
[active] => 1
[position] => 999
[blank] =>
[is_out] =>
)
)
请问一般模板施工经常出现的质量问题有哪一些呢? - 工程施工 - 项目管理 - 氿上知道
返回顶部
满意答案
1、现象
拆除模板后,发现混凝土柱、墙板实际轴线位置与建筑物轴线位置不符。
2、原因分析
(1)放线错误。
(2)柱、墙模板顶部及根部无限位措施,发现偏位不及时纠正,造成累计误差。
(3)无纵向垂直度控制措施。
(4)模板刚度差,螺栓及支撑松动。
二、标高偏差
1、现象
浇筑混凝土时或拆模后,发现模板变形,出现向外凸或翘曲。
2、原因分析
(1)支架支撑在未夯实的基土上,或因基土给水下沉。
(2)模板厚度不够,支撑及围檩间距过大,刚度差。
(3)墙模板的穿墙螺栓直径过小,间距过大,刚度差。
(4)墙模板中的动口内模对撑不牢固,当振捣混凝土时挤偏位。
(5)梁、柱模板卡具间距过大,不能承受振捣混凝土时产生的侧向压力。
(6)混凝土一次浇筑高度过高,下料过快,下料集中,振捣时间过长。
三、标高偏差
1、现象
混凝土结构层标高与图纸设计标高不符。
2、原因分析
(1)木工翻样没考虑装饰装修层厚度。
(2)竖向楼板根部无标高标记或不按标记施工。
(3)模板标高标记或不按标记施工。
(4)结构层无标高控制点。
四、模板拼缝不严密
1、现象
模板间接缝有空隙,混凝土浇筑时漏浆。
2、原因分析
(1)含水率过大,安装时间过长,木模板干缩裂缝。
(2)浇筑混凝土时,木模板没提前浇水湿润,接缝没有胀紧。
(3)模板制作粗糙,拼缝不严密,梁柱接头部位模板尺寸错位、不吻合。
(4)使用已变形的钢模板,边框弯折,接缝措施不当。
五、拆除模板时损坏混凝土
1、现象
拆除模板时将混凝土的边角损坏或碰撞混凝土,造成裂缝。
2、原因分析
(1)混凝土强度低,拆除模板时间过早。
(2)使用拆除后没清理干净的模板,模板上没途刷隔离剂,模板与混凝土有粘结面。
(3)拆除模板时用大锤硬砸或用撬棍硬撬,损坏模板及混凝土。